Field report: harmonic-drive lead times are stretching to 16–26 weeks, and sources point to Tesla's Optimus ramp

A 15-post thread based on talks with harmonic-drive makers, suppliers and robot companies says strain-wave gear lead times are now 16–22 weeks, some 26+, with several sources pointing to Tesla; it estimates 100K Optimus robots would need about 1.4M reducer...

Source: Scobleizer News Pulse (X) · x.com Found via Robert Scoble’s Scobleizer News Pulse · a post on X, not independently verified Published 2026-11-23T03:15:00+00:00 Detected 2026-11-23T06:06:48+00:00
View original source

A 15-post thread based on talks with harmonic-drive makers, suppliers and robot companies says strain-wave gear lead times are now 16–22 weeks, some 26+, with several sources pointing to Tesla; it estimates 100K Optimus robots would need about 1.4M reducer...

A 15-post thread based on talks with harmonic-drive makers, suppliers and robot companies says strain-wave gear lead times are now 16–22 weeks, some 26+, with several sources pointing to Tesla; it estimates 100K Optimus robots would need about 1.4M reducers. None of the sources work at Tesla, so treat it as an...

Hardware and robotics watchers may want to track whether this becomes a product, benchmark, or deployment signal.

Signal Strength 91% Technical label WATCH Public Interest 27 Category ROBOTS & HARDWARE Reader Depth TECHNICAL

Signal Strength reflects source quality, relevance, freshness and evidence. Public Interest helps organize discovery; it is not proof of truth.

Public Interest components
Recognizable Entity Score 0 Practical Impact Score 0 Novelty Interest Score 70 Consequence Score 30 Curiosity Score 68 Shareability Score 21

VQV surfaced this signal because it is recent, relevant to Robotics, connected to Scobleizer News Pulse (X).